Sprint 2 Week 1 – Wheel fit Scrum master
As Emma I would want to be able to collect items and start next level through movement of the chair.
- estimated time: 4 hours
- Acceptance criteria: collect items on collision
- Acceptance criteria: message that says it’s collected
- Acceptance criteria: level loads on correct collision
- Status: <Accepted>
As Steve, a hardcore gamer, I would like an appropriate Level/area for item collection and level start.
- acceptance criteria: snowy terrain
- acceptance criteria: area for items and level load on exit
- estimated time: 2 hours
- status: <Accepted>