AGS Post #5 – Sprint 2 Week 1

Sprint 2 Week 1 – Wheel fit Scrum master

As Emma I would want to be able to collect items and start next level through movement of the chair.

  • estimated time: 4 hours
  • Acceptance criteria: collect items on collision
  • Acceptance criteria: message that says it’s collected
  • Acceptance criteria: level loads on correct collision
  • Status: <Accepted>
Item collection with debug message to confirm working.

Item collection with debug message to confirm working.

Code to destroy game object upon collision and load next level.

Code to destroy game object upon collision and load next level.

Object destroyed on collision with debug message to confirm next level is being loaded

Object destroyed on collision with debug message to confirm next level is being loaded

code showing item collection

code showing item collection


As Steve, a hardcore gamer, I would like an appropriate Level/area for item collection and level start.

  • acceptance criteria: snowy terrain
  • acceptance criteria: area for items and level load on exit
  • estimated time: 2 hours
  • status: <Accepted>
Snowy terrain for item collection level

Snowy terrain for item collection level